Is the time limit for a construction-contract claim five years or ten?
There is no single period for every construction contract. Commercial claims will generally not be heard after five years, subject to exceptions. Civil claims will generally not be heard after ten years, with some shorter special periods. The answer turns on the nature of the right, the competent court and when the right arose.
SourceCommercial Courts Law, Art. 24 (Ministry of Justice legal portal)Civil Transactions Law, Arts. 295 to 297 (Ministry of Justice legal portal)